Ohio approves two data center power plants

State decision follows local opposition, referendum

COLUMBUS — Ohio regulators have approved construction of two large natural gas power plants intended to supply electricity to data centers in central Ohio, including one in a community where voters recently rejected a development agreement involving the project.

The Ohio Power Siting Board approved the facilities Thursday, Nov. 19, in Fairfield and Pickaway counties. Together, the plants would have the capacity to generate up to 2,150 megawatts of electricity.

Both are planned as behind-the-meter facilities, meaning they would supply power directly to nearby data centers rather than operate as traditional power plants selling electricity to the regional grid.

The larger project, Fairfield Energy Center, would be built on 122 acres in Millersport, near Buckeye Lake. It would generate up to 1,350 megawatts of electricity and include a battery storage facility with a power capacity of 1,040 megawatts.

The second project, Ashville Energy Center, would be built on approximately 110 acres in Pickaway County and generate up to 800 megawatts.

Voters reject local agreement

The Ashville approval comes just over two weeks after village voters rejected a development agreement framework involving EdgeConneX, the company developing the associated data center project.

About 82% of voters opposed the measure in the Nov. 3 election, overturning a village resolution establishing terms for negotiations with the developer.

The referendum did not directly revoke the state’s authority to consider the power plant application.

The Ohio Environmental Council criticized the state board’s approval, arguing that residents’ opposition should have carried greater weight in the decision.

Environmental concerns

Residents near both projects have raised concerns about air pollution, noise and the effect of large industrial facilities on surrounding communities.

During a Nov. 10 Ohio Environmental Protection Agency hearing, residents near Millersport questioned the potential effect of emissions on the Buckeye Lake area.

Some expressed concerns that the area’s geography and weather conditions could allow pollutants to remain closer to the ground.

Developers maintain that the facilities would provide dependable electricity to support large data centers. The Fairfield Energy Center developer says the project is designed to comply with environmental requirements and applicable safety standards.

What happens next

The state approvals authorize the projects to move forward under the conditions established by the Ohio Power Siting Board. They do not mean construction is complete or that every other required permit has been issued.

The decisions also highlight a growing disagreement in Ohio over the development of data centers, their electricity demands and how much influence local communities should have over related projects.

Parties to the state proceedings may seek reconsideration of the board’s decisions, with further appeals possible through the Ohio Supreme Court.

Leave a Reply

Your email address will not be published. Required fields are marked *

Create a free account, or log in.

Gain access to read this content, plus limited free content.

Yes! I would like to receive new content and updates.